Monday 30 May 2016 Mosaic Apartments Update

We are happy to advise construction works at 74-76 Kitchener Parade commenced in April 2016, following a 3 month period of design finalisation and construction planning and immediately after the approval of the construction certificate. Project Built were awarded the contract and are running to ...

Read article »

Wednesday 25 May 2016 The Jacob Apartments

The project manager is happy to advise there has been a lot of progress on site since our last update: - The structure is now complete. - Internal fitout on the lower floors has commenced.  - Scaffolding is expected to come down in Mid-May.We anticipate that the building will be comp...

Read article »

Wednesday 18 May 2016 Bankstown Gardens Apartments

We are excited to advise that the external structure is now complete, levels 1-4 are very well advanced with the waterproofing, internal framing set out & windows installed.   The builders are currently working on level 5. The project manager estimates completion of the project will be...

Read article »
Menu openMenu arrowMenu arrow open