Bankstown Gardens, Bakstown


We are excited to advise that the external structure is now complete, levels 1-4 are very well advanced with the waterproofing, internal framing set out & windows installed. The builders are currently working on level 5. The project manager estimates completion of the project will be approximately September this year and settlement of the apartment soon after. We will be in touch shortly with another update. If you have any questions feel free to contact us on 9247 1299.

20 views0 comments

Recent Posts

See All

Aster Apartments, Crows Nest

Project Update September 2018 We are happy to advise that the apartments at Aster, Crows Nest are nearly finished. At this stage, we are...

Ryde Garden, North Ryde Inspections

Please be advised that Pre-Settlement Inspection Invitation for Ryde Garden Building C has been distributed to purchasers. Inspection...